Funding Source |
Project Name |
Project Description |
STATUS |
Anticipated Project Cost |
SANTA MONICA OTHER (Project in SM other than Samohi) |
|
|
Edison Language Academy |
|
|
|
BB |
New Elementary School |
Construct/Replace Elementary School |
Completed |
$ 62,738,388 |
|
|
Land Acquisition |
|
$ 3,540,041 |
|
|
Relocatables |
|
$ 8,248 |
|
|
Temporary Preschool at Rogers |
|
$ 9,430 |
SMS |
Furniture, Fixtures & Equipment (FFE) |
21st century classroom furniture upgrade |
Completed |
$ 800,000 |
SMS |
Safety & Security |
Adding cameras, raptor and other safety upgrades |
Completed |
$ 300,000 |
SMS |
Campus Assessment & Planning |
Master Planning process |
Completed |
$ 90,000 |
SMS |
Edison ES HVAC Improvements |
Installation of new HVAC controls that will optimize the conditioning of interior spaces and the flow of outside air. |
Completed |
$ 168,191 |
SMS |
Edison ES Safety & Security Project - PA/Clock Replacement Project |
Replacement of analogue PA/Clock system with a new IP based PA/Clock system including digital messaging. |
Completed |
$ 72,290 |
Franklin Elementary School |
|
|
|
ES |
Modernization & HVAC |
Window, Paint, Floor and Door Project, HVAC, Fire Alarm & ADA |
Completed |
$ 8,671,209 |
SMS |
Furniture, Fixtures & Equipment (FFE) |
21st century classroom furniture upgrade |
Completed |
$ 900,000 |
SMS |
Safety & Security |
Adding cameras, raptor and other safety upgrades |
Completed |
$ 300,000 |
SMS |
Campus Assessment & Planning |
Master Planning process |
Completed |
$ 200,000 |
SMS |
Campus Plan |
Develop new campus plan |
Completed |
$ 1,578,785 |
ES |
Franklin ES Roofing Replacement Project |
Replacement of roofs on Buildings A and F. |
Completed |
$ 1,289,068 |
SMS |
Franklin ES Safety & Security Project -PA/Clock Replacement Project |
Replacement of analogue PA/Clock system with a new IP based PA/Clock system including digital messaging. |
Completed |
$ 637,351 |
SMS |
New Early Childhood Building |
Construct TK/k classrooms, new field and relocate parking lot (design only) |
In Design |
$ 3,687,293 |
Grant Elementary School |
|
|
|
BB |
Main Entry Reconfiguration |
Security upgrades to entry and main office |
Completed |
$ 548,302 |
ES |
Modernization |
Window, Paint, Floor and Door Project |
Completed |
$ 2,299,681 |
ES |
HVAC & Fire Alarm |
Upgrade HVAC, Electrical, Fire Alarm, & ADA (design only) |
Completed |
$ 303,266 |
SMS |
HVAC & Fire Alarm |
Upgrade HVAC, Electrical, Fire Alarm, & ADA (construction only) |
Completed |
$ 5,000,000 |
SMS |
Furniture, Fixtures & Equipment (FFE) |
21st century classroom furniture upgrade |
Completed |
$ 800,000 |
SMS |
Safety & Security |
Adding cameras, raptor and other safety upgrades |
Completed |
$ 300,000 |
SMS |
Campus Assessment & Planning |
Master Planning process |
Completed |
$ 200,000 |
SMS |
TK Expansion and Modernization |
Transform 4 classrooms into 3 transitional kindergarten classrooms (design only) |
In Design |
$ 3,000,000 |
SMS |
Library Modernization |
Renovate & expand the existing library & innovation classroom (design only) |
In Design |
$ 191,050 |
SMS |
New Classroom Building |
Construct new classroom building with roof top learning garden (design only) |
In Design |
$ 2,314,060 |
McKinley Elementary School |
|
|
|
BB |
Entry and Main Office Reconfiguration |
Security upgrades to entry and main office |
Completed |
$ 1,371,983 |
ES |
Modernization & HVAC |
Window, Paint, Floor and Door Project, HVAC, Fire Alarm & ADA |
Completed |
$ 10,103,157 |
SMS |
Furniture, Fixtures & Equipment (FFE) |
21st century classroom furniture upgrade |
Completed |
$ 800,000 |
SMS |
Safety & Security |
Adding cameras, raptor and other safety upgrades |
Completed |
$ 300,000 |
SMS |
Campus Assessment & Planning |
Master Planning process |
Completed |
$ 200,000 |
SMS |
Safety & Security Project - PA/Clock Replacement Project |
Replacement of analogue PA/Clock system with a new IP based PA/Clock system including digital messaging. |
Completed |
$ 657,488 |
SMS |
New Classroom Building and Administration |
Construction of a new 8 classroom elementary school building and administration offices. |
In Process |
$ 37,380,000 |
Rogers Elementary School |
|
|
|
BB |
Entry and Main Office Reconfiguration |
Security upgrades to entry and main office |
Completed |
$ 397,508 |
ES |
Church Property |
Demo, Parking Lot and Lawn |
Completed |
$ 653,454 |
ES |
Modernization |
Window, Paint, Floor and Door & ADA upgrades |
Completed |
$ 6,443,448 |
ES |
HVAC & Fire Alarm |
Upgrade HVAC, Electrical, Fire Alarm, & ADA (design only) |
Completed |
$ 166,564 |
SMS |
HVAC & Fire Alarm |
Upgrade HVAC, Electrical, Fire Alarm, & ADA (construction only) |
Completed |
$ 4,000,000 |
SMS |
Furniture, Fixtures & Equipment (FFE) |
21st century classroom furniture upgrade |
Completed |
$ 900,000 |
SMS |
Safety & Security |
Adding cameras, raptor and other safety upgrades |
Completed |
$ 250,000 |
SMS |
Campus Assessment & Planning |
Master Planning process |
Completed |
$ 250,000 |
SMS |
Safety & Security Project - PA/Clock Replacement Project |
Replacement of analogue PA/Clock system with a new IP based PA/Clock system including digital messaging. |
Completed |
$ 685,876 |
SMS |
Early Elementary Building Project |
Construction of a new early learning classroom building and play field |
In Process |
$ 24,780,000 |
Roosevelt Elementary School |
|
|
|
ES |
Modernization |
Window, Paint, Floor and Door, Fire Alarm & ADA upgrades |
Completed |
$ 4,009,467 |
ES |
HVAC & Fire Alarm |
Upgrade HVAC, & Electrical (design only) |
Completed |
$ 168,137 |
SMS |
HVAC & Fire Alarm |
Upgrade HVAC, Electrical, Fire Alarm, & ADA (construction only) |
Completed |
$ 3,500,000 |
SMS |
Furniture, Fixtures & Equipment (FFE) |
21st century classroom furniture upgrade |
Completed |
$ 900,000 |
SMS |
Safety & Security |
Adding cameras, raptor and other safety upgrades |
Completed |
$ 300,000 |
SMS |
Campus Assessment & Planning |
Master Planning process |
Completed |
$ 200,000 |
ES |
Roofing Replacement Project |
Replacement of roofs on Buildings A, B, C and E. |
Completed |
$ 1,812,158 |
SMS |
Safety & Security Project - PA/Clock Replacement Project |
Replacement of analogue PA/Clock system with a new IP based PA/Clock system including digital messaging. |
Completed |
$ 680,791 |
SMS |
New Library and Early Childhood Building |
Construct new library and early childhood classrooms (design only) |
In Process |
$ 4,082,950 |
Muir Elementary School/SM Alternative Schoolhouse |
|
|
|
BB |
Emergency Gas Piping Repair |
Repaired/replaced gas lines |
Completed |
$ 108,497 |
BB |
Entry Gate Project |
Security upgrade to entry gate |
Completed |
$ 106,155 |
ES |
Modernization |
Window, Paint, Floor and Door, Fire Alarm & ADA upgrades (design) |
Completed |
$ 130,489 |
ES |
HVAC |
Upgrade HVAC, & Electrical (design only) |
Completed |
$ 250,701 |
SMS |
Modernization & HVAC |
Upgrade HVAC, Electrical, Fire Alarm, & ADA (construction only) |
Completed |
$ 6,500,000 |
SMS |
Furniture, Fixtures & Equipment (FFE) |
21st century classroom furniture upgrade |
Completed |
$ 600,000 |
SMS |
Safety & Security |
Adding cameras, raptor and other safety upgrades |
Completed |
$ 250,000 |
SMS |
Campus Assessment & Planning |
Master Planning process |
Completed |
$ 120,000 |
SMS |
Safety & Security Project - PA/Clock Replacement Project |
Replacement of analogue PA/Clock system with a new IP based PA/Clock system including digital messaging. |
Completed |
$ 680,791 |
SMS |
Water Intrusion Renovation |
Reconstruct campus to be water proof and properly functioning |
In Process |
$ 4,928,466 |
SMS |
Innovation Lab and Administration Renovation |
Renovate 2 classrooms into admin and admin into innovation lab (design only) |
In Process |
$1,634,550 |
Adams Middle School |
|
|
|
BB |
Field Warranty & Defects |
Warranty for synthetic field purchased/installed by SMC |
Completed |
$ 349,075 |
BB |
New Construction & Modernization |
New 80s wing & Main Office, Modernize Art & Principal's Office |
Completed |
$ 25,852,966 |
BB |
Parking Lot |
Construct new parking lot at 16th & Ocena Park |
Completed |
$ 804,654 |
BB |
Relocatables |
Swing Space classrooms and tennis court restore |
Completed |
$ 743,195 |
BB |
Field Site Improvements |
Green Fringe at Perimeter of Athletic Fields |
Completed |
$ 638,509 |
ES & SMS |
Performing Arts Center |
Theater, Choir Room, & Performance Studio Construction |
Completed |
$ 44,200,000 |
ES |
Gym Floor Repacement |
Replace Gym Floor, modernize & ADA upgrades |
Completed |
$ 1,272,753 |
ES |
Synthetic Turf Replacement |
Replace synthetic turf on soccer, football & softball fields |
Completed |
$ 2,318,777 |
ES |
HVAC & Electrical Project - Phase 1 |
Upgrade of HVAC & Electrical for 1/2 campus, Fire Alarm for all |
Completed |
$ 6,201,131 |
SMS |
HVAC & Electrical Project - Phase 2 |
Upgrade of HVAC & Electrical for 1/2 campus, |
Completed |
$ 4,390,482 |
SMS |
Furniture, Fixtures & Equipment (FFE) |
21st century classroom furniture upgrade |
Completed |
$ 1,500,000 |
SMS |
Safety & Security |
Adding cameras, raptor and other safety upgrades |
Completed |
$ 500,000 |
SMS |
Campus Assessment & Planning |
Master Planning process |
Completed |
$ 200,000 |
SMS |
Marquee Replacement Project |
Replace of the original marquee tower and sign. |
Completed |
$ 279,431 |
ES |
Roofing Replacement Project |
Replace of roof on building J |
Completed |
$ 367,892 |
SMS |
Library Renovation |
Renovate the existing library with addition of outdoor learning space |
In Process |
$ 230,835 |
SMS |
New STEAM Building |
Construct new STEM building (design only) includes gym renovation design |
In Process |
$ 2,573,672 |
Lincoln Middle School |
|
|
|
BB |
New Building C & Site Improvements |
New Library & Classroom Building (Pkg 2) |
Completed |
$ 28,440,463 |
BB |
Modernization Building E |
Main Building Classroom & Lab modernization (Pkg 1B) |
Completed |
$ 3,155,016 |
BB |
Relocatables & Site Utilities |
Swing Space Classrooms for construction (Pkg 1A) |
Completed |
$ 770,068 |
ES |
Athletic Field & Track |
Replace Field & Track and Restroom Upgrade |
Completed |
$ 6,675,774 |
ES |
Building G & K Upgrades |
Modernize Special Education and other classrooms (design only) |
Completed |
$ 268,641 |
ES |
HVAC & Electrical Project |
Upgrade HVAC, Electrical & Fire Alarm (design only) |
Completed |
$ 161,844 |
SMS |
HVAC & Electrical Project |
Upgrade HVAC, Electrical & Fire Alarm (construction only) |
Completed |
$ 10,000,000 |
SMS |
Furniture, Fixtures & Equipment (FFE) |
21st century classroom furniture upgrade |
Completed |
$ 1,500,000 |
SMS |
Safety & Security |
Adding cameras, raptor and other safety upgrades |
Completed |
$ 500,000 |
SMS |
Campus Assessment & Planning |
Master Planning process |
Completed |
$ 300,000 |
ES |
Roofing Replacement Project |
Replace of roofs on Buildings D, E, G and H. |
In Process |
$ 1,819,511 |
SMS |
Renovation of Existing 500's Building |
Modernize shops building to be 8th grade project-based learning hub |
In Process |
TBA |
Obama Center (formerly Olympic High School) |
|
|
|
BB |
Demolish Relocatables |
Remove old portable classrooms |
Completed |
$ 51,720 |
BB |
Landscape Improvements |
Improve upper yard after portables demolished |
Completed |
$ 105,362 |
BB |
Modernization |
Improve majority of school |
Completed |
$ 12,674,069 |
ES |
Modernization & HVAC |
Window, Paint, Floor and Door, Fire Alarm, HVAC, ADA (except 4 clrms) |
Completed |
$ 5,395,308 |
ES |
Project Based Learning Upgrades |
Beginning design work for PBL |
Completed |
$ 7,065 |
SMS |
Modernization & HVAC |
Window, Paint, Floor and Door, Fire Alarm, HVAC, ADA (last 4 clrms) |
Completed |
$ 927,904 |
SMS |
Project Based Learning Upgrades |
Completed design and planning |
Completed |
$ 7,500,000 |
SMS |
Furniture, Fixtures & Equipment (FFE) |
21st century classroom furniture upgrade |
Completed |
$ 600,000 |
SMS |
Safety & Security |
Upgrading cameras, raptor and other safety upgrades |
Completed |
$ 6,557 |
Washington CDS, PDLC & FIP |
|
|
|
BB |
Child Development Center Upgrades |
Modernization of Preschools and areas for CDS |
Completed |
$ 1,790,058 |
BB |
Washington South Facilities Building |
Repair and Modernization for CDS & FIP |
Completed |
$ 449,073 |
ES |
Washington West Moderization |
Window, Paint, Floor and Door, Fire Alarm, HVAC, ADA of CDS & PDLC |
Completed |
$ 1,172,974 |
SMS |
Washington West Moderization |
Window, Paint, Floor and Door, Fire Alarm, HVAC, ADA of CDS & PDLC |
Completed |
$ 2,410,887 |
SMS |
Furniture, Fixtures & Equipment (FFE) |
21st century classroom furniture upgrade |
Completed |
$ 150,000 |
SMS |
Safety & Security |
Adding cameras, raptor and other safety upgrades |
Completed |
$ 100,000 |
ES |
Washington West WPFD & HVAC Project |
Installation of new HVAC controls that will optimize the conditioning of interior spaces and the flow of outside air. |
Completed |
$ 59,744 |
SANTA MONICA HIGH SCHOOL |
|
|
|
Samohi |
|
|
|
|
BB |
New Science & Technology Building |
Innovation Building and site improvements |
Completed |
$ 93,186,883 |
ES |
Campus Plan |
Master Planning the full campus buildout |
Completed |
$ 4,176,020 |
ES & SMS |
Construct Phases 1 & 2 |
Discovery and Site work, plus added parking |
Completed |
$ 185,000,000 |
ES |
Barnum Hall Repairs & Upgrades |
Campus Plan upgrades for Barnum Hall |
Completed |
$ 1,000,000 |
ES |
Football Field & Track Lighting |
Upgrade field lighting to LED & controls |
Completed |
$ 139,671 |
ES |
HVAC & Electrical Project |
Upgrade HVAC in buildings in use for 10+ years |
Completed |
$ 8,962,188 |
ES |
Interim Repairs/Upgrades |
Various small projects needed for continued use of campus during SCP |
Completed |
$ 2,173,877 |
SMS |
Athletic Field Replacement |
New synthetic turf carpet for football field |
Completed |
$ 855,972 |
ES |
Interim Softball Field |
Adding Softball Field to Sealy Field and other upgrades |
Completed |
$ 4,349,925 |
ES |
Science Quad Synthetic Turf |
Upgrade science quad for us during construction |
Completed |
$ 113,067 |
ES |
Path of Travel Upgrades |
Adding stairs & ramps to science quad |
Completed |
$ 113,067 |
ES |
Solar Project |
Adding photovoltaic panels to Innovation & battery backup |
Completed |
$ 1,500,000 |
SMS |
Furniture, Fixtures & Equipment (FFE) |
21st century classroom furniture upgrade |
Completed |
$ 2,000,000 |
SMS |
Safety & Security |
Adding cameras, raptor and other safety upgrades |
Completed |
$ 6,000,000 |
SMS |
Utility Infrastructure |
part of Safety & Security |
Completed |
$ 750,000 |
BB |
New Science & Technology Building |
Innovation Building and site improvements |
Completed |
$ 93,186,883 |
ES |
Campus Plan |
Master Planning the full campus buildout |
Completed |
$ 4,176,020 |
ES & SMS |
Construct Phases 1 & 2 |
Discovery and Site work, plus added parking |
Completed |
$ 185,000,000 |
ES |
Barnum Hall Repairs & Upgrades |
Campus Plan upgrades for Barnum Hall |
Completed |
$ 1,000,000 |
ES |
Football Field & Track Lighting |
Upgrade field lighting to LED & controls |
Completed |
$ 139,671 |
ES |
HVAC & Electrical Project |
Upgrade HVAC in buildings in use for 10+ years |
Completed |
$ 8,962,188 |
ES |
Interim Repairs/Upgrades |
Various small projects needed for continued use of campus during SCP |
Completed |
$ 2,173,877 |
SMS |
Athletic Field Replacement |
New synthetic turf carpet for football field |
Completed |
$ 855,972 |
ES |
Interim Softball Field |
Adding Softball Field to Sealy Field and other upgrades |
Completed |
$ 4,349,925 |
ES |
Science Quad Synthetic Turf |
Upgrade science quad for us during construction |
Completed |
$ 113,067 |
ES |
Path of Travel Upgrades |
Adding stairs & ramps to science quad |
Completed |
$ 113,067 |
ES |
Solar Project |
Adding photovoltaic panels to Innovation & battery backup |
Completed |
$ 1,500,000 |
SMS |
Furniture, Fixtures & Equipment (FFE) |
21st century classroom furniture upgrade |
Completed |
$ 2,000,000 |
SMS |
Safety & Security |
Adding cameras, fire-alarms, electronic locks and other safety upgrades |
Completed |
$ 6,000,000 |
SMS |
Utility Infrastructure |
Installing infrastructure for campus build-out |
Completed |
$ 750,000 |
SMS |
English, Business and Art Gallery |
Installing transformer in English, repurposing Business and Creating Art Gallery |
Completed |
$ 4,192,998 |
SMS |
Exploration and Gold Gym |
New academic Building and Gold Gym to replace South Gym |
In Progress |
$ 127,213,000 |
SMS |
North Gym Access Controls |
Installing electronic access controls |
Completed |
$ 130,607 |
SMS |
Phase 4a English Building Renovation |
Renovation reuse of existing building to accommodate Samohi Administration |
On Hold |
$ 3,000,320 |
SMS |
Phase 4b New Student Center/Student Services |
Replace business building with new student center/student services building (design only) |
In Process |
TBA |
MALIBU |
|
|
|
|
Webster Elementary School |
|
|
|
BB |
Fire Alarm Replacement |
Replace Fire Alarm - Safety & Security |
Completed |
$ 467,350 |
BB |
Drop-off & Parking Lot Reconfiguration |
Redesign the lower + mid parking lots and drop off areas - Safety |
Completed |
$ 5,131,262 |
ES |
Modernization |
Window, Paint, Floor and Door & ADA upgrades |
Completed |
$ 4,005,157 |
ES |
HVAC |
Upgrade HVAC, & Electrical (design only) |
Completed |
$ 244,341 |
M |
HVAC & Electrical |
Upgrade HVAC, Electrical (construction only) |
Completed |
$ 2,506,609 |
M |
Furniture, Fixtures & Equipment (FFE) |
21st century classroom furniture upgrade |
Completed |
$ 600,000 |
M |
Safety & Security |
Adding cameras, raptor and other safety upgrades |
Completed |
$ 300,000 |
M |
Sewer Connection |
Connection to Malibu Sewage Treatment Plant |
Postponed |
$ 500,000 |
M |
Campus Assessment & Planning |
Master Planning process |
In Process |
$ 280,400 |
Malibu Elementary School (formerly Point Dume Science School) |
|
|
|
BB |
Gas Line & Furnace Replacement |
Repairs gas lines and updates heating system |
Completed |
$ 1,018,510 |
BB |
Wastewater Treatment |
Repair of Septic System |
Completed |
$ 110,066 |
ES |
Modernization & HVAC |
Window, Paint, Floor and Door & Fire Alarm, HVAC, ADA upgrades |
Completed |
$ 5,525,540 |
ES |
Malibu Alignment |
Elementary Schools alignment & Playground Project |
Completed |
$ 5,146,835 |
M |
Furniture, Fixtures & Equipment (FFE) |
21st century classroom furniture upgrade |
Completed |
$ 600,000 |
M |
Safety & Security |
Adding cameras, raptor and other safety upgrades |
Completed |
$ 300,000 |
Cabrillo Elementary School (now part of Malibu Middle/High School) |
|
|
|
BB |
Safety Project |
Fence & Gate Safety & Security upgrades |
Completed |
$ 555,604 |
ES |
Modernization |
Window, Paint, Floor and Door & ADA upgrades |
Completed |
$ 2,216,907 |
Malibu Middle/High School |
|
|
|
BB & ES |
Building AB/C Replacement & E Replacement |
Construct New Library/Classroom/Admin Bldg & New Classroom Bldg |
Completed |
$ 97,285,142 |
BB |
New Parking Lot |
Construct 150 space parking lot |
Completed |
$ - |
BB |
Off-Site Traffic |
Required Traffic improvements offsite |
Completed |
$ - |
BB |
Wastewater treatment |
upgrades to septic and wastewater systems |
Completed |
$ - |
BB |
Water District 29 |
Water service upgrade (offsite package) |
Completed |
$ 462,752 |
BB |
Soil Remediation |
Replace soil with PCBS |
Completed |
$ 426,448 |
BB |
Upgrade Fire Alarm |
Replace & rewire fire alarm system |
Completed |
$ 2,014,274 |
ES |
Safety & Security |
Adding cameras, raptor and other safety upgrades |
Completed |
$ 5,175 |
ES |
Malibu Alignment |
Reorganization of Malibu schools |
Completed |
$ 2,983,730 |
M |
Furniture, Fixtures & Equipment (FFE) |
21st century classroom furniture upgrade |
Completed |
$ 4,600,000 |
M |
Safety & Security |
Adding cameras, raptor and other safety upgrades |
Completed |
$ 1,800,000 |
M |
Malibu Campus Plan - Phase 1 |
Master Planning Malibu MS/HS Campus Plan & construct Phase 1 |
Completed |
$ 157,494,600 |
M |
Malibu Campus Plan - Phase 2 |
Master Planning Malibu MS/HS Phase 2 (design only) |
Completed |
$ 4,000,000 |
M |
Interim Measures |
Interim Measures, including required PCB abatement |
Completed |
$ 2,000,000 |
M |
Malibu Campus Plan Interim Measures |
Modular Village Relocation |
Completed |
$ 968,300 |
M |
Bulding E and I-Art Program Relocation of Klin |
Improvements to Bldg. E and I Art classrooms and Construction of new kiln enclosure |
Completed |
$ 1,093,565 |
M |
New High School Building-Phase 1 |
Construction of a new 75,0009 SF, 2-story high school building |
In Process |
$ 149,500,000 |
M |
New Middle School Recreation Center/MPR and Aquatices Facility |
Construction of new middle school recreation center/MPR, innovation lab, kitchen, eating area, wellness center, life skills classrooms and new aquatic center (design only) |
In Process |
$ 4,239,000 |
TECHNOLOGY |
|
|
|
Distictwide |
|
|
|
BB |
Data Center |
Preliminary project |
Completed |
$ 75,198 |
BB |
Data Center Districtwide Technology |
Construct and implement districtwide data center |
Completed |
$ 8,280,686 |
ES |
21st Century Classrooms |
updates classrooms for 21st century technology |
Completed |
$ 10,953,440 |
ES |
Computer Lab Upgrades |
modernizes computer labs throughout district |
Completed |
$ 2,511,600 |
ES |
Infrastructure |
updates technological backbone to IT operations |
Completed |
$ 10,792,103 |
ES |
Leadership & Capacity Building |
Professional Development training on new technology |
Completed |
$ 3,384,922 |
ES |
Library |
Library upgrades with 21st century tech |
Completed |
$ 2,139,738 |
ES |
SBAC & Initial 1-1 devices |
devices for students |
Completed |
$ 4,432,555 |
|
|
|
|
|
School Site Technology |
|
|
|
BB |
Edison Technology |
21st Century technology upgrades |
Completed |
$ 156,293 |
BB |
Franklin Technology |
21st Century technology upgrades |
Completed |
$ 322,805 |
BB |
Grant Technology |
21st Century technology upgrades |
Completed |
$ 304,739 |
BB |
McKinley Technology |
21st Century technology upgrades |
Completed |
$ 247,495 |
BB |
Rogers Technology |
21st Century technology upgrades |
Completed |
$ 233,720 |
BB |
Roosevelt Technology |
21st Century technology upgrades |
Completed |
$ 295,518 |
BB |
Muir/SMASH Technology |
21st Century technology upgrades |
Completed |
$ 344,847 |
BB |
Webster Technology |
21st Century technology upgrades |
Completed |
$ 230,307 |
BB |
Malibu ES Technology |
21st Century technology upgrades |
Completed |
$ 259,144 |
BB |
Cabrillo Technology |
21st Century technology upgrades |
Completed |
$ 255,267 |
BB |
Adams Technology |
21st Century technology upgrades |
Completed |
$ 1,024,691 |
BB |
Lincoln Technology |
21st Century technology upgrades |
Completed |
$ 1,107,591 |
BB |
Obama Technology |
21st Century technology upgrades |
Completed |
$ 208,196 |
BB |
Malibu HS Technology |
21st Century technology upgrades |
Completed |
$ 757,818 |
BB |
Samohi Technology |
21st Century technology upgrades |
Completed |
$ 1,486,619 |
BB |
Transportation Technology |
21st Century technology upgrades |
Completed |
$ 5,588 |
BB |
Washington Technology |
21st Century technology upgrades |
Completed |
$ 54,356 |